painting project template
Repaint Exterior Wall
Prep and repaint one exterior wall of a single-storey house (~30 sqm). Covers pressure washing from the ground with an extension lance, scraping, priming bare patches and applying two coats of exterior acrylic paint.
Difficulty: intermediate. Estimated working time: 14 hours.
Estimated materials cost: AUD 428. Indicative AU source pricing, not a quote. Local prices, tools, labour and site requirements can change the total.
Use this templateA starting plan, not a complete build-safety manual. Selection checks authored data and dimensions, not a physical prototype. Review measurements, local requirements and task safety before building. Working time excludes unrecorded drying, curing and waiting.
Overview
6 phases and 10 material lines to review and edit in your own project.
Original template reference. Not to scale.
Static reference only. If you edit project dimensions, use your current measurements, not this drawing.
Preparation/readiness flow, not an empty coating-coverage rectangle. Stop for lead assessment before disturbing old paint; wash from ground, wait for a fully dry wall, repair and remove dust, mask, prime, dry, then first/second coats. Arrows show sequence, not guaranteed drying times. Product recoat instructions and safe access remain authoritative; source W is the wall vertical extent.
| Source dimension | Value |
|---|---|
| length | 1000 cm |
| width | 300 cm |
L: source length. W: source width. H: source height. Use the table to identify each extent. Detail cut, stock and relationship measurements use the stored metric plan, converted to decimal inches in imperial view; they are not the separately rounded imperial task plan.
Instruction label sources
- Test for lead paint (task: phase-01-task-01, title)
- standing on the ground (task: phase-01-task-03, title)
- wall is fully dry (task: phase-01-task-04, description)
- Brush or blow away dust (task: phase-02-task-05, title)
- Mask all window glass (task: phase-03-task-01, title)
- Apply primer (task: phase-04-task-01, title)
- Check tin for recoat time. (task: phase-04-task-02, description)
- Roll first coat (task: phase-05-task-02, title)
- Allow to dry (task: phase-05-task-04, title)
- Roll second coat (task: phase-06-task-02, title)
Instruction context: Pressure wash & assess. Test for lead paint before scraping or sanding if the house was built before 1997. Pressure wash wall from top to bottom, standing on the ground. Allow wall to dry completely (24-48 hours)
Scrape, sand & repair: Brush or blow away dust
Mask & protect: Mask all window glass, door frames and trim
Spot-prime bare areas: Apply primer to all bare substrate, sanded areas and caulked joints. Allow primer to dry (2-4 hours)
First coat: Roll first coat onto wall panels. Allow to dry (4-6 hours or overnight)
Second coat & clean up: Roll second coat onto wall
Materials
- Lead Paint Test Kit: 1 kit
- Exterior Acrylic Paint 10L: 1 tin
- Exterior Primer/Sealer 4L: 1 tin
- Painter's Masking Tape 48mm: 3 rolls
- Masking Paper/Plastic 1.4m × 20m: 1 roll
- Drop Sheets Heavy Duty 3.6×2.7m: 3 sheets
- Exterior Gap Filler (paintable caulk): 2 tubes
- Sandpaper 80-grit sheets: 5 sheets
- Paint Roller Sleeve 270mm (long nap 18mm): 2 each
- Extension Pole 1.2-2.4m: 1 each
Cut-list summary
No structured cut list is recorded for this plan. Measure the site and follow the phase instructions before ordering or cutting.
Phase summary
1. Pressure wash & assess
Clean the wall and identify all areas needing repair
- Test for lead paint before scraping or sanding if the house was built before 1997
Warning: paint sold in Australia before 1997 can contain lead, and dry sanding or power sanding it releases lead dust. Swab-test each colour layer in several spots with a lead test kit from a paint shop or hardware store. If any swab reads positive, do not dry sand or dry scrape: keep the surface wet, catch every chip on the drop sheets, and engage a lead paint removalist for large areas.
- Lay drop sheets along base of wall to protect garden/paving
Extend at least 2m from wall.
- Pressure wash wall from top to bottom, standing on the ground
Fit the extension lance or wand approved by the pressure washer's manufacturer and keep both feet on the ground for the whole wash. Keep nozzle 300mm from surface. Remove dirt, mould, cobwebs and loose paint. Do not operate the pressure washer from any raised surface: the recoil can unbalance you. If any part of the wall is beyond the lance's reach from the ground, leave it and engage a professional exterior cleaner for that area.
- Allow wall to dry completely (24-48 hours)
Do not proceed until wall is fully dry. Moisture causes peeling.
- Mark areas with peeling paint, cracks or bare substrate
These need scraping and spot-priming.
- Test for lead paint before scraping or sanding if the house was built before 1997
2. Scrape, sand & repair
Remove loose paint and repair surface defects
- Scrape all loose and peeling paint back to a firm edge
Use paint scraper. Feather edges with sandpaper.
- Wire-brush any areas with mould or chalky residue
Ensure surface is sound before priming.
- Sand glossy areas with 80-grit for adhesion
The new paint needs mechanical tooth to grip.
- Caulk gaps around window frames, trim and joints
Use paintable exterior caulk. Smooth with wet finger. Apply it with a caulking gun.
- Brush or blow away dust
Clean surface is critical for primer adhesion.
- Scrape all loose and peeling paint back to a firm edge
3. Mask & protect
Tape off windows, trim and adjacent surfaces
- Mask all window glass, door frames and trim
Press tape edges firmly. Use masking paper for large glass areas.
- Cover downpipes, taps and light fittings
Wrap with plastic and tape.
- Reposition drop sheets for painting phase
Ensure full coverage along wall base.
- Mask all window glass, door frames and trim
4. Spot-prime bare areas
Prime all bare substrate and repaired sections
- Apply primer to all bare substrate, sanded areas and caulked joints
Use brush for edges, small roller for larger patches.
- Allow primer to dry (2-4 hours)
Check tin for recoat time. Primer seals porous surfaces.
- Apply primer to all bare substrate, sanded areas and caulked joints
5. First coat
Apply first full coat of exterior paint
- Cut in around all windows, trim and edges with brush
Work top to bottom. Maintain a wet edge. Use the ladder, set on firm level ground, only for brush cut-in along the eaves line; roll the rest from the ground on the extension pole.
- Roll first coat onto wall panels
Use long-nap roller on extension pole. W-pattern, even pressure.
- Check for runs and sags, lay off while wet
Step back regularly to spot drips.
- Allow to dry (4-6 hours or overnight)
Exterior paints need longer dry time. Check weather forecast.
- Cut in around all windows, trim and edges with brush
6. Second coat & clean up
Apply final coat and remove masking
- Cut in second coat around all edges
Same pattern as first coat.
- Roll second coat onto wall
Consistent coverage. Don't overwork; lay off in one direction.
- Remove masking tape before paint fully cures
Pull at 45° angle. If paint has dried, score along tape edge with knife.
- Touch up any misses or tape bleed-through
Small brush for detail work.
- Clean all tools, fold drop sheets, dispose of waste properly
Don't pour paint down drains. Let residue dry in tin before disposal.
- Cut in second coat around all edges