Weld an indoor 1200x600x900mm steel-frame workbench with a plain steel top. About 9 to 13 hours of hands-on labour, plus cooling and fire-watch time. For makers already trained in welding, not a first welding lesson. No load rating. The AUD estimate buys full stock and consumable packs; tools, PPE, delivery, cutting services and power are excluded.

Difficulty: intermediate. Estimated working time: 11 hours.

Estimated materials cost: AUD 337.53. Indicative AU source pricing, not a quote. Local prices, tools, labour and site requirements can change the total.

Use this template

A starting plan, not a complete build-safety manual. Selection checks authored data and dimensions, not a physical prototype. Review measurements, local requirements and task safety before building. Working time excludes unrecorded drying, curing and waiting.

Overview

4 phases and 5 material lines to review and edit in your own project.

Original instruction and dimension reference

Original template reference. Not to scale.

Static reference only. If you edit project dimensions, use your current measurements, not this drawing.

Top plan: square-butt cross rails fit between full-length long rails, never mitred. Section inset separates outside tube size from wall thickness. Height stack: legs under frame, plate flush with zero overhang. Tube vents and balanced hot-work sequence remain mandatory in the linked tasks; weld profiles and any load rating are omitted.

Original metric dimensions
Source dimensionValue
length120 cm
width60 cm
height90 cm

L: source length. W: source width. H: source height. Use the table to identify each extent. Detail cut, stock and relationship measurements use the stored metric plan, converted to decimal inches in imperial view; they are not the separately rounded imperial task plan.

Instruction label sources
  • Between long rails: 520 mm (cut: part-02, length)
  • Outside tube: 40 mm (material: material-01, width)
  • Tube wall: 2.5 mm (material: material-01, wallThickness)
  • Top plate: 3 mm (cut: part-06, thickness)
  • Height stack: 900 mm (relationship: height-stack, total)
  • square butt-joint cuts (task: phase-02-task-01, description)
  • zero overhang (task: phase-04-task-02, description)

Instruction context: Weld, attach the top and inspect. Weld the frame joints in a balanced sequence. Fit the top plate flush and stitch it from below

Mark, cut and deburr parts: Cut 2 top long rails at 1200mm from 40x40mm steel SHS

Related cut parts
  • part-01: Top long rails
  • part-02: Top cross rails
  • part-03: Legs
  • part-04: Lower long rails
  • part-05: Lower cross rails
  • part-06: Top plate

Materials

  • 40x40mm uncoated mild steel SHS 8m (2.5mm wall): 2 lengths
  • 3mm mild steel plate 2400x1200mm: 1 sheet
  • Cigweld WG0908 gasless MIG wire 0.8mm 0.9kg spool: 1 roll
  • Flexovit 125mm cutting discs 1mm (10 pack): 1 pack
  • Josco 125mm 60 grit abrasive flap disc: 1 piece

Cut-list summary

  • Top long rails: 2 × 1200 × 40 × 40 mm; 40x40mm uncoated mild steel SHS 8m (2.5mm wall)
  • Top cross rails: 3 × 520 × 40 × 40 mm; 40x40mm uncoated mild steel SHS 8m (2.5mm wall)
  • Legs: 4 × 857 × 40 × 40 mm; 40x40mm uncoated mild steel SHS 8m (2.5mm wall)
  • Lower long rails: 2 × 1120 × 40 × 40 mm; 40x40mm uncoated mild steel SHS 8m (2.5mm wall)
  • Lower cross rails: 2 × 520 × 40 × 40 mm; 40x40mm uncoated mild steel SHS 8m (2.5mm wall)
  • Top plate: 1 × 1200 × 600 × 3 mm; 3mm mild steel plate 2400x1200mm

Phase summary

  1. 1. Plan and make hot work safe

    Confirm stock, workspace and welding competence before cutting. No electrical installation, plumbing, lifting equipment or structural work is part of this plan.

    • Review the plan, prices and intended use

      Build an indoor, free-standing workbench for light hand assembly only. It has no certified load rating, flatness guarantee or anchorage design. Do not use it as a step, lifting support, vehicle stand or welding fixture. The estimate buys full stock and consumable packs, not tools, PPE, electricity, delivery or supplier cutting. Check current local quotes before ordering.

    • Set up ventilation, fire protection and PPE for welding and grinding

      Use local fume extraction suitable for welding, a welding helmet with the correct shade, safety glasses, hearing protection, leather gloves, non-flammable clothing and closed leather footwear. Use respiratory protection selected for the exposure; it does not replace extraction. Screen bystanders from arc UV. Remove combustibles, check both sides of nearby walls and floors, keep an appropriate inspected extinguisher ready and arrange a fire watch during and after hot work under the site rules. Stop if safe fume or fire control cannot be provided.

    • Check uncoated stock and practise the weld on offcuts

      Use only the specified uncoated mild steel SHS and plate, never galvanised, painted or unknown scrap. Wipe oil away and let surfaces dry; never use chlorinated cleaner around welding. Practise single-pass welds on matching wall and plate thickness with the WG0908 wire. Follow the welder and wire makers for polarity, setup and technique, rather than a guessed current. If you cannot produce sound joints, get hands-on welding instruction before continuing. Use an existing suitable protected outlet; a licensed electrician must handle any outlet or wiring changes.

  2. 2. Mark, cut and deburr parts

    Allow a 3mm saw kerf per separation, including the metal-cutting blade. Clamp stock and support both the work and offcut; stop if the actual kerf is wider than the allowance. Mark each finished part label before moving it.

    • Cut 2 top long rails at 1200mm from 40x40mm steel SHS

      Use a metal-cutting bandsaw, or the guarded grinder with its rated cutting disc. All tube cuts are square butt-joint cuts, not mitres. Use the 40x40mm uncoated mild steel SHS 8m (2.5mm wall). Stock A supplies one top long rail, one lower long rail, two legs and three cross rails; stock B supplies the remaining parts. Each stock retains more than 2000mm after the 3mm kerfs; keep the surplus for practice and future projects.

    • Cut 3 top cross rails at 520mm from 40x40mm steel SHS

      Two end cross rails fit between the full-length rails, with their outside faces flush to the rail ends. The third is centred along the top length. The width closes as 40 + 520 + 40 = 600mm. Do not subtract the tube wall thickness from the outside section size.

    • Cut 4 legs at 857mm from 40x40mm steel SHS

      The legs sit underneath the top frame at its four outside corners, not inside it. Height: 857mm leg + 40mm top frame + 3mm plate = 900mm. There are no castors, feet or pads in this height stack.

    • Cut 2 lower long rails at 1120mm from 40x40mm steel SHS

      These fit between the front and rear pairs of legs: 40 + 1120 + 40 = 1200mm. Keep all long faces in the same outside planes as the top frame.

    • Cut 2 lower cross rails at 520mm from 40x40mm steel SHS

      These fit between the left and right pairs of legs: 40 + 520 + 40 = 600mm. They do not run between the lower long rails.

    • Cut 1 top plate at 1200mm x 600mm from the mild steel plate

      Use the 3mm mild steel plate 2400x1200mm. Keep the full 1200mm stock width as the finished top length and crosscut a 600mm strip from the 2400mm direction. After a 3mm kerf the offcut is 1797x1200mm. The full sheet is heavy: use suitable mechanical handling or arrange supported supplier cutting and requote it. Never balance it on an improvised stand.

    • Deburr every edge with the flap disc and check the labelled parts

      Fit the Flexovit cutting discs only for straight supported cuts and the Josco flap disc for deburring. Inspect discs, retain the guard and side handle, respect disc speed ratings and keep sparks away from people and combustibles. Never side-load a cutting disc. Unplug the grinder before changing discs, wear eye and face protection, and do not grind away welds to hide defects.

    • Drill a 6mm vent hole in every tube member before assembly

      Use a metal drill bit and clamp each of the 13 tube members. Place a permanent vent on an underside or inward face 20mm from an end, clear of the intended weld. Remove swarf and keep each hole open through assembly and use. Several cross rails have both ends closed by adjoining tube walls, so open leg bottoms alone do not vent the whole frame. Never weld a sealed hollow section.

  3. 3. Tack the frame and verify geometry

    Clamp on a level non-combustible surface. Tack only until all dimensions, diagonals and leg contact have been checked; do not use the bench yet.

    • Tack the top frame square at 1200x600mm

      Lay the two top long rails parallel, place end cross rails between them flush at both ends, and centre the third cross rail at 600mm from either end to its centreline. Keep their top faces coplanar. Clamp, compare corner-to-corner diagonals and adjust until equal before tacking. Verify the outside length and width after each tack.

    • Stand and tack the legs beneath the four top corners

      Use clamps and supports, not a person holding a hot joint. Keep all four leg outside faces flush with the top frame outside faces. Check perpendicularity in both planes. Keep tube ends open while welding; never weld a sealed hollow section. Do not cap the leg bottoms.

    • Tack the lower rails with their undersides 150mm above the floor

      The lower rail tops are 190mm above the floor. Fit the lower long rails between front and rear legs and the lower cross rails between side legs. All joints meet leg faces, so no lower rail overlaps another. Check diagonals on the top and both vertical planes and check four-foot contact without forcing the frame.

  4. 4. Weld, attach the top and inspect

    Complete sound joints using the tested setup. Alternate opposing joints and let the frame cool naturally to control distortion; cooling is elapsed time, not labour.

    • Weld the frame joints in a balanced sequence

      Use the Cigweld WG0908 gasless MIG wire and the proven single-pass setup on clean metal. Alternate sides and corners, remove slag with a chipping hammer and wire brush, and inspect each joint. Do not quench or grind sound welds flush. Stop for qualified repair advice if any joint is cracked, porous, undercut, incompletely fused or distorted. Leave tube openings vented throughout hot work.

    • Fit the top plate flush and stitch it from below

      Clamp the plate flat on the top frame with zero overhang. On the underside, use short 20mm welds at the midpoint of each outer rail and at both ends of the centre cross rail, six stitches in total. Alternate opposite sides and let each area cool before proceeding. Leave unwelded gaps; do not seal the plate perimeter or enclose the tube ends. This is a light assembly surface, not a certified welding or impact table.

    • Inspect cool joints, stability and the finished dimensions before use

      Check 1200x600x900mm overall, equal diagonals, no sharp edges and contact on all four legs on a level floor. If it rocks, racks or has a defective weld, stop and correct the cause before use; do not hide it with added load. Keep the bare steel indoors and dry, remove rust before it advances, and inspect joints before each use. Do not claim a safe load from these dimensions or from a retailer comparator. Keep the fire watch until the site hot-work checks are complete.