tiling project template

Tile Shower Surround

Tile three walls of a 90cm × 90cm shower recess from floor to 210cm height using ceramic wall tiles. Covers demolition, waterproofing, tile layout, cutting, adhesive application, grouting and sealing. The first row rests on a batten propped on the shower floor and taped to the wall, so nothing is fixed through the membrane, and the membrane and adhesive manufacturers' dry and cure times gate each covering step.

Difficulty: intermediate. Estimated working time: 19 hours.

Estimated materials cost: AUD 740. Indicative AU source pricing, not a quote. Local prices, tools, labour and site requirements can change the total.

Use this template

A starting plan, not a complete build-safety manual. Selection checks authored data and dimensions, not a physical prototype. Review measurements, local requirements and task safety before building. Working time excludes unrecorded drying, curing and waiting.

Overview

6 phases and 17 material lines to review and edit in your own project.

Original instruction and dimension reference

Original template reference. Not to scale.

Static reference only. If you edit project dimensions, use your current measurements, not this drawing.

Layer/sequence reference, not a certified waterproofing specification: sound cement sheet, primer, corner band and two membrane coats, drying/inspection, then adhesive and tiles. The inset depicts layered order only, never a screw through the membrane. Confirm licensed-work scope first. No new plumbing, glass screen or waterproofing certificate is implied.

Original metric dimensions
Source dimensionValue
length90 cm
width90 cm
height210 cm

L: source length. W: source width. H: source height. Use the table to identify each extent. Detail cut, stock and relationship measurements use the stored metric plan, converted to decimal inches in imperial view; they are not the separately rounded imperial task plan.

Instruction label sources
  • cement sheet (task: phase-01-task-03, title)
  • substrate primer (task: phase-02-task-02, title)
  • waterproof band tape (task: phase-02-task-03, title)
  • right angles to first (task: phase-02-task-05, title)
  • pinholes, thin spots and damage (task: phase-02-task-07, title)
  • licensed waterproofer (task: phase-02-task-01, title)
  • adhesive (task: phase-04-task-01, title)
  • Set tiles (task: phase-04-task-02, title)

Instruction context: Layout and cut tiles. Dry-lay a row of tiles along the back wall to find the centre line and cut widths

Demolish existing surface: Inspect substrate: replace any water-damaged plasterboard with cement sheet

Waterproof shower recess: Check whether your state requires a licensed waterproofer for this shower. Prime all cement sheet surfaces with substrate primer. Apply waterproof band tape to all internal corners and floor-wall junctions. Apply second membrane coat at right angles to first after drying: minimum 1mm total thickness. Inspect the dry membrane for pinholes, thin spots and damage, and repair any defect with the same membrane system

Install tiles: Spread adhesive with 6mm notched trowel on rear wall: work in 50cm × 50cm sections. Set tiles from the propped batten upward: insert 2mm spacers at every joint

Materials

  • Ceramic Wall Tiles 300×100mm (subway format): 7 sqm
  • Flexible Wall Tile Adhesive 20kg: 2 bags
  • Tile Grout 3kg (sanded, mould-resistant): 2 bags
  • Waterproof Membrane (liquid applied) 4L: 2 tins
  • Waterproof Band Tape 10m: 2 rolls
  • Tile Spacers 2mm: 2 bags (200pc)
  • Silicone Sealant (bathroom grade, mould-resistant): 2 tubes
  • PTFE thread tape: 1 roll
  • Fibre Cement Sheet 2400×1200×6mm (if required): 2 sheets
  • Notched Trowel 6mm: 1 each
  • Grout Float: 1 each
  • Tile Trim (aluminium, 2.4m lengths): 3 lengths
  • Primer/Sealer for Substrate 1L: 1 tin
  • Grout Sealer Spray 500ml: 1 bottle
  • Pine batten 42×19mm 2.4m (temporary datum support): 2 lengths
  • Plastic packers (assorted, pack of 100): 1 pack
  • Painter's tape 24mm: 1 roll

Cut-list summary

No structured cut list is recorded for this plan. Measure the site and follow the phase instructions before ordering or cutting.

Phase summary

  1. 1. Demolish existing surface

    Remove old tiles, adhesive and damaged substrate from the 90cm × 90cm shower recess walls.

    • Turn off water supply and remove shower fittings (mixer, shower head, flanges)

      Warning: cap exposed pipe threads with tape to prevent debris entering the plumbing.

    • Remove existing tiles with a cold chisel and hammer: work top down

      Warning: wear safety glasses, gloves and a dust mask. Tile shards are razor-sharp.

    • Inspect substrate: replace any water-damaged plasterboard with cement sheet

      Tip: press firmly on the wall surface; spongy areas indicate moisture damage and must be cut out.

  2. 2. Waterproof shower recess

    Apply two coats of liquid waterproof membrane to all shower walls and floor junction, then let it dry and inspect it before any tiling. Elapsed (dry): the membrane manufacturer's stated dry time, which is not labour.

    • Check whether your state requires a licensed waterproofer for this shower

      Warning: bathroom waterproofing is licensed work in most Australian states, and Queensland requires a licensed waterproofer unless you hold an owner-builder permit for the property. Where DIY is allowed the membrane must still meet AS 3740, and an uncertified membrane can void an insurance claim for water damage. Check your state building authority before you open the membrane tin.

    • Prime all cement sheet surfaces with substrate primer

      Allow primer to dry for the time specified on the product, usually 1-2 hours.

    • Apply waterproof band tape to all internal corners and floor-wall junctions

      Bed the tape into a wet coat of membrane, with no dry spots or bubbles.

    • Apply first coat of liquid membrane to walls up to 180cm and full shower floor

      Warning: membrane must extend at least 150mm beyond the shower opening on each side wall.

    • Apply second membrane coat at right angles to first after drying: minimum 1mm total thickness

      Tip: tint the second coat a different colour so you can see complete coverage.

    • Wait before tiling until the membrane manufacturer's stated dry time has passed

      Read the dry time off the membrane tin, because it differs between products and lengthens in cold or humid weather. Both coats and the band tape in the corners must be dry before anything is placed against the membrane.

    • Inspect the dry membrane for pinholes, thin spots and damage, and repair any defect with the same membrane system

      Check every corner, the band tape edges and the area around each pipe penetration. Nothing in this template is fixed through the membrane, so treat any hole or fixing mark as a defect: coat it with the membrane to the manufacturer's repair instructions and let the repair dry for the stated time before it is covered.

  3. 3. Layout and cut tiles

    Plan tile placement for three walls to minimise cuts and centre the pattern.

    • Dry-lay a row of tiles along the back wall to find the centre line and cut widths

      Tip: adjust the layout so cut tiles at each end are at least half a tile wide and never less than 40mm.

    • Mark a level datum line at one tile height from the floor on all three walls, then stand a propped batten on it

      Do not fix anything through the membrane. Cut a 42×19mm pine batten to each wall length, stand it on edge on the shower floor on plastic packers so its top edge meets the datum line, check it with the spirit level and hold it to the wall with painter's tape at each end and in the middle. The first full row rests on the batten while the adhesive sets, and the membrane stays unbroken.

    • Pre-cut tiles for pipe penetrations using a tile hole saw or grinder

      Run the hole saw in the drill/driver at low speed and keep the tile wet to cool the bit. Warning: always cut tiles in a well-ventilated area and wear a P2 dust mask.

  4. 4. Install tiles

    Adhere tiles to shower walls using flexible tile adhesive with consistent spacing. Elapsed (cure): the adhesive manufacturer's cure time, once before the batten comes out and again before grouting; neither is labour.

    • Spread adhesive with 6mm notched trowel on rear wall: work in 50cm × 50cm sections

      Tip: back-butter each tile lightly for full adhesive coverage behind the tile.

    • Set tiles from the propped batten upward: insert 2mm spacers at every joint

      Check plumb and level every 3-4 rows. Adjust before adhesive begins to set.

    • Tile side walls, fitting cut tiles neatly into internal corners

      Leave a 3mm gap in internal corners; this will be filled with silicone, not grout.

    • Wait before removing the batten until the adhesive manufacturer's cure time has passed

      Read the cure time off the adhesive bag. The rows above the batten must carry their own weight before the support comes out, or the bottom joint closes up and the rows slide.

    • Remove the batten, packers and tape, inspect the membrane along the floor junction, then tile the bottom row with cut tiles to floor level

      Peel the painter's tape off slowly and check the membrane behind it and under the batten for scuffs, lifted band tape or any hole. Repair a defect with the membrane to the manufacturer's instructions and let the repair dry for the stated time before the bottom row covers it. Tip: measure each bottom tile individually, because floors are rarely perfectly level.

    • Wait before grouting until the adhesive manufacturer's cure time has passed for the bottom row

      The bottom row went in last, so its adhesive is the youngest in the shower. Grouting or wetting it early can shift the tiles and trap moisture under the grout.

  5. 5. Grout and seal

    Fill tile joints with mould-resistant grout and seal all movement joints with silicone.

    • Mix grout to a thick paste and press into all joints with a grout float at 45°

      Work diagonally across the tiles to avoid pulling grout out of joints.

    • Sponge-wash tiles after 15-20 minutes to remove grout haze

      Tip: rinse the sponge frequently and use minimal water, because excess water weakens grout.

    • Apply bathroom silicone to all internal corners and floor-wall junctions

      Tip: mask both sides of the joint with painters tape for a clean line. Remove tape immediately after tooling.

    • Apply grout sealer spray after 72 hours curing

      Warning: do not use the shower for at least 24 hours after grouting and 72 hours before sealing.

  6. 6. Refit fittings and test

    Reinstall the shower fittings over the new tiles, restore the water and check every joint for leaks.

    • Refit the mixer flange and handle, then the shower arm and head, sealing each flange to the tiles with silicone

      Wrap the shower arm thread with PTFE tape before threading it in. Warning: if the mixer body or pipework now sits too deep or too proud for the tiles, moving it is licensed plumbing work, so book a licensed plumber.

    • Turn the water back on and leak-check every fitting under pressure

      Run the shower hot and cold for 5 minutes, then press dry paper towel behind each flange and around the shower arm. Fix any drip before the first shower.